King Hussein International Airport/ Aqaba Rehabilitation and maintenance.

Category: Done Projects

Rehabilitation and mentainance of the existing 3.2 KM runway (45m width and 7.5 sholders each side) including reinstatement of the surface asphalt layer with 7cm thickness and applying of 2 layers of SBS asphalt with 4cm and 6cm, all painting works, lighting works and earth works for stability of side slopes

Number Of Tenders 28/2010
Name Of Tenders King Hussein International Airport/ Aqaba Rehabilitation and maintenance.
Owner Aqaba Development Company
Engineer/ Supervisor Associated Consulting Engineers
Contract Value 5,995,000.000
Final Value 6,653,221.82
Starting Date -0001-11-30
Period 300